ITICCOL was in charge of the inspection and evaluation of storage tanks under API 653, inspection by NDT techniques such as MFL, Ultrasound, and corrosion mapping, among others, and evaluation of tank settlement using topography pursuant to Annex B of API 653

PRIMAX

THE SALVADOR TEST

ITICCOL carried out Electroluminescence (EL) processes and I-V curves.

THE SALVADOR TEST

CELSOLAR PANAMA

ITICCOL audited the construction of the photovoltaic solar generation plant in David, Panama.

CELSOLAR PANAMA

PLASTICEL

Plasticel Jumbo - Valle del Cauca. ITICCOL carried out inspection and thermography with drones to photovoltaic solar parks.

PLASTICEL

CHEVRON

ITICCOL carried out non-destructive tests (drone inspection) at Chevron facilities in Buenaventura.

CHEVRON

PRAXAIR

ITICCOL carried out thickness evaluation on ammonia pipe systems at the Barrancabermeja plant.

PRAXAIR

GENSA

ITICCOL supervised the construction of the largest photovoltaic plant in the unconnected areas of INIRIDA

GENSA

CELSIA

ITICCOL supervised the construction of the PV CSE Plant in El Espinal.

CELSIA

GREEN YELLOW & VENTUS

ITICCOL carried out the audit of the medium voltage line and the thermography service in Planeta Rica - Petals of Cordoba - evacuation line